The site plan for replacement of docks A through E. Four docks will replace five, but the average slip length will increase. According to the timeline dated August 4 2004, on-site reconstruction of docks H and I begins in mid-February of 2005 and will be completed by Mid-May. The on-site work on docks A through E begins in mid-May and and should be finished by the end of October '05. Plans are to phase the work so that a minium number of boats are displaced at any one time - but berthing will still be very tight next summer. previous photo - - - - - - - - - - - - next photo |